Each activity currently either on schedule or a few days ahead of schedule
In June and July, site preparation encountered several surprises
In August, digging of hole and shoring largely proceeded as expected, except:
Installation of water main by city complicated logistics
Accomplished goal of having all utilities rerouted before classes resumed
Geopiers should be finished by end of this week
Pads over geopiers to be started this week and continue through mid-October
Foundation walls will start shortly, after first pads prepared
With tower crane in place, concrete pumper not needed very much for pouring concrete (in contrast to work at Joe Rosenfield Center)
|